Los Lunas Activity Updates

Posted on: May 17, 2021

[ARCHIVED] Local Street Improvements

The Village is always working to improve our local roads by resurfacing the roads and correcting issues with utilities and sidewalks.  Don Federico Road, Luna Hill Road, Vaisa Road/NM 314 and Taylor Road have all recently been completed. As of May 2021, the following roads are on the schedule:

  • Appaloosa Road - Design complete 
  • Cinder Road - Design complete; scheduling construction start. 
  • Mesa Cruzada/Mesa Loop, - Design complete; awaiting project start. 
  • Willow/Nieto Road - Design complete; awaiting bid.
  • Gensen Drive - Design complete; awaiting bid.
  • Mission Road - In design. 
  • Rivas Road- Design complete; scheduling construction start.
  • Camino de Higino - Design complete; scheduling construction start. 
  • Pandora Drive - In design.